You are required to read and agree to the below before accessing a full-text version of an article in the IDE article repository.
The full-text document you are about to access is subject to national and international copyright laws. In most cases (but not necessarily all) the consequence is that personal use is allowed given that the copyright owner is duly acknowledged and respected. All other use (typically) require an explicit permission (often in writing) by the copyright owner.
For the reports in this repository we specifically note that
- the use of articles under IEEE copyright is governed by the IEEE copyright policy (available at http://www.ieee.org/web/publications/rights/copyrightpolicy.html)
- the use of articles under ACM copyright is governed by the ACM copyright policy (available at http://www.acm.org/pubs/copyright_policy/)
- technical reports and other articles issued by M‰lardalen University is free for personal use. For other use, the explicit consent of the authors is required
- in other cases, please contact the copyright owner for detailed information
By accepting I agree to acknowledge and respect the rights of the copyright owner of the document I am about to access.
If you are in doubt, feel free to contact webmaster@ide.mdh.se
The Importance of Information Transfer Between Project Phases
Publication Type:
Conference/Workshop Paper
Venue:
3rd International Conference on Ship & Offshore Technology - India 2013
Abstract
This research investigates the subject of current shipbuilding practices and two offshore structures projects, focusing on information transfer between project process phases. Large construction projects, as offshore structures, are often subjected to substantial economic and environmental risks. A holistic approach to the project execution could help mitigate some of the problems that yards, engineering firms and marine contractors face today. Research has been conducted into the area of EPC offshore structures projects and the need for predictability, shortened lead times and increased flexibility. The literature study performed as background to this research, shows that there are few studies covering information management between offshore structures project phases. A case study was performed to further explore and enrich the empirical findings. Concluding that information is insufficient between project phases, looking ahead, the question is raised: In what way can information be improved between project phases?
Bibtex
@inproceedings{Sjogren3757,
author = {Peter Sj{\"o}gren and Monica Bellgran and Bj{\"o}rn Fagerstr{\"o}m},
title = {The Importance of Information Transfer Between Project Phases},
month = {December},
year = {2013},
booktitle = {3rd International Conference on Ship {\&} Offshore Technology - India 2013},
url = {http://www.ipr.mdu.se/publications/3757-}
}