You are required to read and agree to the below before accessing a full-text version of an article in the IDE article repository.
The full-text document you are about to access is subject to national and international copyright laws. In most cases (but not necessarily all) the consequence is that personal use is allowed given that the copyright owner is duly acknowledged and respected. All other use (typically) require an explicit permission (often in writing) by the copyright owner.
For the reports in this repository we specifically note that
- the use of articles under IEEE copyright is governed by the IEEE copyright policy (available at http://www.ieee.org/web/publications/rights/copyrightpolicy.html)
- the use of articles under ACM copyright is governed by the ACM copyright policy (available at http://www.acm.org/pubs/copyright_policy/)
- technical reports and other articles issued by M‰lardalen University is free for personal use. For other use, the explicit consent of the authors is required
- in other cases, please contact the copyright owner for detailed information
By accepting I agree to acknowledge and respect the rights of the copyright owner of the document I am about to access.
If you are in doubt, feel free to contact webmaster@ide.mdh.se
Engineering Change Management in Engineering-To-Order Projects from a Manufacturing Perspective
Publication Type:
Conference/Workshop Paper
Venue:
Swedish Production Symposium 2014
Abstract
The purpose of this research was to investigate the engineering change management process in engineering-to-order projects while comparing the same process in traditional manufacturing. A single-case study at a engineering-to-order – engineering review office was performed and results were analysed in conjuction with literature covering the engineering change process in traditional manufacturing. Engineering-to-order projects and tradional manufacturing are different in many ways but share the need for a reliant engineering change process. This study found that engineering change management post-change analysis could benefit future projects in the form of quantifiable lessons learned from previous project’s engineering change data.
Bibtex
@inproceedings{Sjogren3755,
author = {Peter Sj{\"o}gren and Monica Bellgran and Bj{\"o}rn Fagerstr{\"o}m},
title = {Engineering Change Management in Engineering-To-Order Projects from a Manufacturing Perspective},
month = {September},
year = {2014},
booktitle = {Swedish Production Symposium 2014},
url = {http://www.ipr.mdu.se/publications/3755-}
}